Your application should be supported by:
- a Geotechnical report
- a site specific plan indicating the type and location of the system
These documents should be attached to your completed New or Alter/Modify a Sewage Management System application form. You will be contacted to pay the relevant fee once your application has been assessed.
You will also need to obtain a copy of the current NSW Health Accreditation available from NSW Health.
Once an approval of installation is issued, work may commence. As Council is responsible for ensuring the installation the proposed system is in accordance with the specifications and the geotechnical report a number of mandatory inspections are required at certain stages of the installation process.
At completion a final inspection will be conducted and an Approval to Operate will be issued. The Approval to Operate gives an approval period of 2 years for a new or modified system.